B192 between Neubrandenburg and goods: blocking from July for construction work!

B192 between Neubrandenburg and goods: blocking from July for construction work!
In the Mecklenburg Lake District region, there is a major traffic adjustment. From the end of July, the important federal road B192 between Neubrandenburg and goods will be completely closed for several weeks. The reason for this are the necessary renovation work , which include renovation of the road as well as the renovation of a passage in the section between Penzlin and Krukow. The work is created for a period of ten weeks and are carried out under full closure.
The decision to put the construction work on the summer vacation was made to minimize the restrictions for school transport and commuters. This strategic approach has proven itself in the past, as the previous construction work on the section between Möllenhagen and Penzlin showed, which already provided detours and inconvenience in the surrounding villages.
planned diversion routes
The effects of the full closure are regulated via two diversion routes:
- Eastern detour: About Peckatel (B193), Flower Wood (L34) and Neubrandenburg (B96).
- western detour: About Klein Plasten (B192), Stavenhagen (B194) and Neubrandenburg (B104).
These diversions will play a critical role in order to maintain the flow of traffic during the construction period and avoid traffic jams. However, the exact implementation of the construction work is still in the award procedure, so that the exact schedule is set to the construction company after the contract is issued.
other construction sites in the region
Although the B192 remains the main connection in the region, additional construction projects are also being planned. For example, the state road L281 between Woldegk and Friedland from the 31st calendar week is fully blocked for ten weeks. Miss and asphalt work also take place here. The List of construction sites of the traffic information service also shows numerous other construction sites in the area.
An overview of the current construction sites in Mecklenburg-Western Pomerania, which should consider road users, can be viewed on the page of Verkehrslage.de . In this region, an extensive package of measures for the roadway repair is implemented to make the streets more secure and more comfortable.
We keep readers up to date on the progress in the B192 and other construction sites. It remains to be hoped that the necessary work will proceed quickly and that traffic in the region will soon be able to flow smoothly again.
Details | |
---|---|
Ort | Neustrelitz, Deutschland |
Quellen |